Köselitz · Saxony-Anhalt
Data-center and energy concept
Project details
- Total site considered
- approximately 270 haOverall site area in the 2025 concept.
- Full-build-out scenario
- up to 540 MW ITIT-capacity scenario examined in the May 2025 concept.
- Solar generation
- approximately 170 MWpSolar capacity envisaged in the concept, including agrivoltaics.
- Development approach
- Modular campusExpansion aligned with demand and progress on site requirements.
Site and land-use concept
The site had originally been earmarked for a holiday park. The revised concept examined a combination of digital infrastructure and power generation. The work considered how to allocate land between these uses and divide the development into independently usable sections. The overall site area needed to be distinguished from the land allocated to each proposed use. The technical concept divided the possible full build-out into five modular data-center buildings.
Power supply and development phases
For the full-build-out scenario of 540 MW of IT load, the technical concept calculated approximately 675 MW of total electrical demand at a power usage effectiveness (PUE) of 1.25. It envisaged approximately 170 MWp of solar capacity, partly as agrivoltaics, and modular battery storage with around 100 MW of power and 200 MWh of energy capacity. Storage was intended to limit peak demand and support the use of solar power. Direct-to-chip and immersion cooling were considered for high-density IT loads, alongside potential uses for waste heat. Proximity to a 380-kV transmission line prompted technical grid enquiries; no binding connection capacity had been secured.
Phased development was intended to align land requirements and capital expenditure with actual demand for data-center capacity. Investment and operating cost scenarios made it possible to compare different allocations of land and sequences of development.
Project materials and coordination
DMS Development analysed the site and market, compared the options financially and prepared an investment memorandum with supporting materials. It presented the concept to prospective investors, answered questions and coordinated next steps with the owner. Planning and environmental questions were assembled for the next stage of development; a technical enquiry submitted to the transmission-grid operator clarified the requirements for a connection line, potential grid connection points and further assessment.
Concept work undertaken in 2025. Area and capacity figures are planning assumptions; planning permissions and a binding grid connection remained to be clarified.
Open project profile